By Engr. Ch. Waseem Sajjad 2×660MW Coal-fired Power Plants at Port Qasim Karachi Progress update: • Financial Closed (FC) achieved. • Civil works on site started in May 2015. • Jetty completed. • Plant 2 months ahead of schedule. • Energization in October 2017. • Expected Commercial Operation Date …